Installation Qualification
(IQ) |
||
|
System
Information |
||
|
1.
System Requirements (mfg. recommended) |
1.
O/S Requirements… 2.
Other software requirements… 3.
CPU requirements… 4.
Memory requirements… 5.
Other hardware requirements… |
|
|
2.
Configuration Requirements |
[specify
default settings. attach list if
necessary] |
|
|
3.
System Specifications |
Test Machine |
Production Machine |
|
Type A: [machine name] |
Type B: [machine name] |
|
|
Software: ·
O/S version x.x ·
Other sw version y.y ·
Etc… Hardware ·
CPU speed/type ·
yyyMb Ram ·
Other hw… |
Software: ·
O/S version x.x ·
Other sw version y.y ·
Etc… Hardware ·
CPU speed/type ·
yyyMb Ram ·
Other hw… |
|
|
4.
System Configuration |
[specify
any changes to default settings. Attach
list if necessary] |
[specify
any changes to default settings. Attach
list if necessary] |
|
5.
Migration Plan (test box to production) |
[Describe
the milestones that must be successfully completed and documented prior to
moving the system into production] |
|
Installation
Plan |
||
|
1.
Installer |
John
Doe |
|
|
2.
Date Installed |
3/19/2003 |
|
|
3.
Hardware/Software Compatibility |
IQ
Successful. COTS
v4.1.1 system requirements have been found to be compatible with the hardware
and software utilized for installation in the test and production
environment. |
|
|
Operation Qualification
(OQ) |
||
|
Functionality/Test
Requirements |
||
|
1.
Machine Identification |
Type
X: [machine name] |
|
|
Software: ·
O/S version x.x ·
Other sw version y.y ·
Etc… Hardware ·
CPU speed/type ·
yyyMb Ram ·
Other hw… |
||
|
2.
Time line/responsibility for completion |
Project
Manager: Jane Smith §
See Project Timeline (attached) |
|
|
3.
Matrix – functionality versus test used to verify |
[tests
must ensure requirements of system operate as expected. describe or attach functionality vs. test
matrix. summarize the testing process, which can also be documented in the
map] |
|
|
4.
Compatibility statement |
OQ
successful, results communicated. [include
compatibly statement, such as The comparisons of the actual results vs. the
comparator results were found to have no significant differences.] |
|
|
Training
Plan |
||
|
1.
User notification |
[describe
how users will be trained in use of system. attach email of training notice,
dates of training, email of how to use, enhanced functionality of this
version, etc.] |
|
|
Communication
Plan |
||
|
1.
User notification |
[describe
how users will be told system is available. attach or link to notification
notice] |
|
|
2.
Notification of identified bugs and resolutions |
[list
any identified and/or known bugs, and how they were resolved, or should be
managed] |
|
Performance Qualification (PQ) |
||
|
Implementation
Plan |
||
|
1.
User Verification Testing Plan and timeline |
[describe
or refer to user verification test plan, include specifics of performance
testing] |
|
|
2.
Accessibility |
[list
directions on how to access] |
|
|
3.
Limitation to universal effectivity? |
[note
any limitations on user access, e.g. number licenses, specific machines, permissions,
appropriate training req’d, etc.] |
|
|
4.
Effectivity Date |
[date
software was put into production] |
|